my today cs605 paper .
total 26 question thy 20 mcqs and 6 subjective thy .
MCQs past main se ak bi nai tha bt easy thy
Q1: Give any two characteristics of risk? 2 marks
Q2: In context of function points which elementary process sends data or control information outsides the application boundary? 2 marks
Q3: Discuss some uses of control charts? 3 marks
Q4: For a certain project the value of TSS set selector TSS was 2.6, so as for TSS values the degree of rigor for this project falls both in structured as well as in strict categories. Now the project manager can select the degree of rigor for this project? 3 marks
Q5: Using the work accomplished formula in context of relationship between people and effort prove that the work accomplished by team of seven (7) people will be less than the work accomplished by the team of four (4) people when the communicate overhead per channel is 5%? 5 marks
Q6: Calculate the lack of ambiguity? 5 marks
Nf=25 , Nnf=5, Nui=10
total 26 question thy 20 mcqs and 6 subjective thy .
MCQs past main se ak bi nai tha bt easy thy
Q1: Give any two characteristics of risk? 2 marks
Q2: In context of function points which elementary process sends data or control information outsides the application boundary? 2 marks
Q3: Discuss some uses of control charts? 3 marks
Q4: For a certain project the value of TSS set selector TSS was 2.6, so as for TSS values the degree of rigor for this project falls both in structured as well as in strict categories. Now the project manager can select the degree of rigor for this project? 3 marks
Q5: Using the work accomplished formula in context of relationship between people and effort prove that the work accomplished by team of seven (7) people will be less than the work accomplished by the team of four (4) people when the communicate overhead per channel is 5%? 5 marks
Q6: Calculate the lack of ambiguity? 5 marks
Nf=25 , Nnf=5, Nui=10